Board President Jerry Clink called the meeting to order at 7:00pm.

Members Cheryl Nagel and Dave Wensink were present, as well as BPA Clerk Sarah Schroeder.

Visitor(s): Frank Wittenmyer was in attendance with further questions about his electric meter and the several months of billing fluctuation. Mr. Clink again reiterated that the meter was tested by the City of Bowling Green and they found no issues. Frank felt that regardless of what the test showed, it was obvious that there was a problem between November ’23 and February ’24. He brought his bills with him for October through April, which were (in order) $24.36, $129.14, $220.91, $6.23, $296.15, $104.30, then $55.50. Jerry had pulled the meter for testing after the $296.15 bill, and Frank stated that the readings seemed more accurate with the new meter. He did not pay the bills for $296.15 and $104.13 while the meter was being tested, and was very upset about having to cover the past due balance (although fees were waived until the result was received). The board decided to go ahead and issue a credit to Frank’s account for $400.45, in case there was a reading error or another discrepancy, although unlikely, that was not caught by the testing. Mr. Wensink made a motion for the write off, which was seconded by Ms. Nagel; all were in favor. The next bill should reflect the updated amount owed.

Mr. Wittenmyer left the meeting at 7:19pm.

The minutes from the previous meeting (5/7/24) were reviewed by the board.

Mr. Wensink made a motion to approve them as read, and Ms. Nagel seconded; all were in favor.

Financial Items

  • 18 vouchers were approved and signed by members of the board:
  • Jerry Clink: May payroll (51 hours @ $40/hour) $ 2,040.00
  • Kevin Berry: May payroll (40 hours @ $40/hour) $ 1,600.00
  • Tim Brubaker: May payroll (4 hours @ $40/hour) $ 160.00
  • Roger Vanscoder: May payroll (3.5 hours @ $16/hour) $ 56.00
  • Sarah Schroeder: May payroll (BPA Clerk salary) $ 400.00
  • AMP-Ohio, Inc: April 2024 power billing $ 13,065.02
  • WEX Bank / Marathon Fleet: Bucket truck fuel $ 41.72
  • Hoops Bros Trash Removal: Trash service for June $ 56.94
  • Ohio Business Gateway: Outside kWh tax for April $ 15.00
  • Ohio Business Gateway: Outside kWh tax for May $ 11.00
  • Power Line Supply: Electric supplies (2 invoices) $ 5,175.30
  • Postmaster: Stamps for electric bills (6 rolls of 100) $ 408.00
  • Alicia Villegas: Refund of electric deposit (22855 Defiance Pk) $ 175.00
  • Jerry Clink: Reimbursement for WC Landfill fees $ 15.98
  • Elan Financial Services (VISA) / Carter Lumber:

Supplies for transformer cover (aka “doghouse”) $ 726.13

  • Jerry Clink: Reimbursement for Carter Lumber bill-

Additional supplies for transformer cover (aka “doghouse”) $ 649.00

  • Tri-County Tarp: Custom tarp for town truck $ 407.25
  • Hoops Bros Trash Removal: Trash service for July $ 56.06
  • The adjustment report for 5/8/24-6/12/24 was presented for the board’s review. There was 1 adjustment made since the last meeting. Mr. Wensink moved to approve the report, and Ms. Nagel seconded; all were in favor. It was signed by Mr. Clink.
  • The board was brought up to date on delinquent accounts. There were 2 shutoff notices issued last month, and partial payments were received for both. There were 3 shutoffs sent at the beginning of this month, all with a deadline of 6/18/24.
  • The Clerk discussed the fact that there have been several bank errors in relation to the BPA checking account (#19). It may be necessary to change the account number in order to prevent future errors, since it is only 2 digits. The board was fine with this.

Old Business

Jerry updated the board on the status of our current projects…

  • The “doghouse” transformer cover is now complete and has been set in place.
  • No estimated have been received for the garage doors yet. Two contractors have been called; one hasn’t showed up yet, and the other had to reschedule.
  • They haven’t started construction on the maintenance building lean-to yet, but they plan to get the supplies before the end of the month.

New Business

The bucket truck will be out of service for a couple weeks for repair. The City of Bowling Green will provide mutual aid/use of their trucks in the meantime if needed.

No further business was brought before the board.